Ingraham High School Addition; Seattle, WA

PROJECT: Ingraham High School Addition; 1819 N. 135th Street; Seattle, WA 98133

OWNER: Seattle School District No. 1; Facilities Department
OWNER’S PROJECT MANGER: Shiels Obletz Johnsen, Inc.
GC/CM: Cornerstone General Contractors, Inc

Contact: Bryan Gormley
Phone: (425) 652-2341
Email: bryan@cornerstonegci.com

ARCHITECT: Integrus Architecture

For the following bid packages, sealed bids must be received at Cornerstone General Contractor’s offices, located at 11805 N. Creek Parkway South, #115, Bothell, WA 98011 on March 1, 2018 by 3:00 PM. Bids will be publicly opened immediately thereafter.

https://cornerstonegci.com/bid-room/

BID PACKAGE; BUDGET; DESCRIPTION

BP-04.1; $275,000; Masonry

BP-06.1; $640,000; Casework & Finish Carpentry

BP-07.1; $810,000; Metal Panels, Siding & Flashings

BP-07.2; $2,500,000; Roofing

BP-08.1; $890,000; Curtainwall, Storefront & Glazing

BP-09.1; $1,100,000; Framing & GWB

BP-09.2; $470,000; Acoustical Ceilings & Treatments

BP-09.3; $143,000; Resilient & Carpet Flooring

BP-09.4; $130,000; Tile Flooring

BP-09.5; $190,000; Painting, Coatings & Sealants

BP-21.1; $256,000; Fire Sprinklers

BP-22.1; $3,300,000; Mechanical

BP-26.1; $1,900,000; Electrical

BP-31.1; $520,000; Site Development

BP-32.1; $150,000; Landscape & Irrigation

BOND GUARANTEE: A bid bond in the amount of 5% of the base bid amount is required on all bids exceeding $300,000.

PERFORMANCE BOND: All bid packages $300,000 or greater require payment and performance bonds on the forms provided in Section 005213 – Form of Contract.

BID DOCUMENTS: Bid Contractors may obtain one set of plans and specifications from ARC Reprographics upon receipt of a refundable deposit of $200.00 made payable to Cornerstone General Contractors, Inc.

ARC Document Solutions
2730 Occidental Ave S
Seattle, WA 98134

Phone: (206) 622-6000

Closing Date: 
Thursday, March 1, 2018