MBDA-Tacoma Business Center is inviting construction firms to meet with Korsmo Construction and learn about subcontracting opportunities on these two Tacoma Public Schools projects.

***Local, minority, and woman-owned firms are encouraged to attend!

Register today - space is limited! Register here

Meeting dates and scopes covered:

May 1

  • Demolition
  • Abatement
  • Site Construction
  • Utilities and Earthwork

June 13

  • Structure
  • (Concrete, Structural Steel, Wood Framing)
  • CMU and brick veneer
  • Mechanical
  • Electrical
  • Fire Protection
  • Food Service Equipment
  • Doors and Hardware
  • Aluminum Hardware
  • Drywall and Insulation

July 2

  • Painting
  • Acoustical Ceiling
  • Landscaping
  • Flooring(Tile, Carpet, Resilient Flooring)

Grant Center for the Expressive Arts Project Details:

Projected budget: $29 million
Square feet: 55,060
Architect: McGranahan Architects
Design: September 2016 - March 2018
Contractor: Korsmo Construction
Construction: June 2018 - August 2019
Expected opening: Fall 2019
Read more here: https://www.tacomaschools.org/construction/Pages/GrantElementarySchool.aspx

Boze Elementary School Replacement Project Details:

Projected budget: $32 million
Architect and contractor: BCRA and Korsmo
Design: April 2018 - July 2019
Construction: May 2019 - August 2020
Expected opening: Fall 2020
Read more here: https://www.tacomaschools.org/construction/Pages/BozeElementarySchool.aspx