A. This Project will provide a re-configuration of Gate A9 and remove obstructions at Gate A8 for it to function as designed with a 777-200ER aircraft.

B. The Project will include a new fixed walkway section at Gate A9 to connect to the re-located Rotunda and Passenger Loading Bridge. There will be demo of existing PCCP Panels to provide for new footing locations and pour back, new walkway support column, demo of and installation of Bollards, demo and relocation of Mechanical & Electrical piping and components, and demo and restriping at the ramp level. More Information