Invitation to Bid: Renton High School Phased Science Rooms Modernization
Invitation to Bid: Renton High School Phased Science Rooms Modernization
Project Address: 400 S 2nd Street, Renton, WA 98057
Virtual Subcontracting outreach event via Teams February 21, 2023 @ 11:00 AM.
Contact Carrie Whitton to get registered: carriew@formacc.com
The new RENTON HIGH SCHOOL PHASED SCIENCE ROOMS MODERNIZATION PROJECT is a 18,200 SQ FT tenant improvement to existing science classrooms on the 1st & 3rd floors of the main classroom building (Building A) of Renton High School. Work includes the complete demolition and interior tenant improvement of 8 new science classrooms in two distinct and separate areas of Renton High School. Work involves all new finishes and equipment as well as all new mechanical and electrical systems throughout the modernized spaces. Selected building envelope, roof, and mechanical penthouse improvements associated with the new spaces are also included. The work will occur during occupied and non-occupied timeframes in an active high school.
Must comply with State of Washington prevailing wage requirements.
NTP for construction activity to begin at the job site is approximately June 26, 2023.
Phase 1 Substantial Completion December 15, 2023
Full Project Substantial Completion July 12, 2024
Bid Date/Time: Wednesday, March 22, 2023 @ 1:00pm – 3:00pm at Renton School District FOMC - 7812 S 12th St. Seattle, WA 98178
Questions contact Jesse Favia, Project Manager via email at jessef@formacc.com or (206) 965-5646
Documents will be available on BXWA on or around March 1, 2023 http://www.bxwa.com/bxwa_toc/private/2372/toc.html
FORMA Construction Company is an equal opportunity employer and requests bids from all subcontractors and suppliers, including minority and women-owned businesses; disadvantaged and disabled veterans; and emerging small business enterprises.