RFP: Elwha River Bridge - Bridge Replacement Project
Johansen Construction Company (JCC) is requesting quotes from Subcontractors & Suppliers for the following project:
Project Name: Elwha River Bridge – Bridge Replacement
Owner: Washington State Department of Transportation
Bid Closing Date: December 21, 2022, 11:00 AM
Subcontractor/Supplier Quote Due Date: November 20, 2022
DBE Condition of Award Goal: 17%
Project Duration: 330 Working Days
Bids to be submitted to: estimating@johansencci.com or via fax at (360) 829-5473
Point of Contact: Questions you have for JCC can be emailed to: estimating@johansencci.com, or you may call our office at 360-829-6493 and ask for Andy Smith in our Estimating Department.
Project Description: This contract provides for the improvement of 0.70 miles of US 101 Clallam County, MP 239.23 to MP 239.93 by constructing a 3-span precast concrete girder bridge and removing the existing 3-span concrete arch bridge. The Work includes clearing and grubbing, grading, construction access, drainage, media filter drains, biofiltration swale, soldier pile and geosynthetic walls, surfacing, hot mix asphalt, high friction surface treatment, erosion control, roadside restoration, roadside seeding, compost temporary stream diversion for bridge removal and engineered log jams, pavement markers, guideposts, removing and installing guardrail, illumination, signing, pavement marking, providing and maintaining temporary traffic control, implementing a traffic detour, engineered log jam install, and other work.
Subcontractor/Supplier Opportunities Include (but are not limited to): clearing & grubbing, erosion control, existing bridge demolition, traffic control, HMA paving, planing, striping, landscaping, hauling, signage, hydro seeding, guardrails, traffic barriers, bridge railing, geosynthetic retaining walls, concrete fascia panels, soldier pile supply & install, large diameter bridge shafts, dewatering, electrical, survey, structural concrete, flatwork concrete, engineered log jam installation, stream diversion, permanent signage, and fencing. As well as the supply of ready-mix concrete, pipe/utilities/precast structures, aggregate, prestressed concrete girders, and disposal.
JCC encourages bids from all subcontractors and suppliers including Disadvantaged Business Enterprises (DBE’s), for any item of work, or portion of an item, or combination thereof related to this project.
Bid Documents can be viewed at:
https://ftp.wsdot.wa.gov/contracts/9891-ElwhaRiverBridgeBridgeReplacement/