Pier 91 Berths J, K, L and M Fender System Replacement - Seattle
SUB-BIDS & SUPPLY QUOTES REQUESTED FOR
Pier 91 Berths J, K, L and M Fender System Replacement
PACIFIC PILE & MARINE, LP
BID DATE: March 10TH AT 2:00PM
700 S. RIVERSIDE DR. SEATTLE, WA 98108
Phone: (206) 331-3873 FAX: (206) 774-5958
Subcontractor/Supplier Prices Due March 9, 2021
ESTIMATING COORDINATOR: KATIE LABORDE/ EMAIL: KATIEL@PACIFICPILE.COM
Project Description: Replacement of 1,270’ of failing timber fender system at the northwestern face of Pier 91 (Berths J, K, L & M) with a steel fender system.
- Demolish and dispose of existing fender system complete
- Remove and dispose of existing fender piles complete
- Provide and install new galvanized steel fender piles
- Provide and install HDPE jackets on all new piles
- Provide and install new fender system complete
- Provide coatings
Subcontract opportunities include, but are not limited to; Diving; Trucking and Disposal, Surveying; Supply of Fabricated Metals; Supply of Piling; Coating; Environmental & Erosion Control Monitoring, and other scopes.
WMBE Utilization Goal of 3%
Pacific Pile & Marine (PPM), intends to negotiate in good faith with all certified WBE and MBE firms to encourage participation, including tailoring packages to better fit firms’ capabilities. Please contact us regarding any assistance needed with this solicitation including obtaining bonding, insurance requirements, lines of credit, necessary equipment, badging, and materials/supplies. We are signatory to Operating Engineers, Laborers, Carpenters and Pile Drivers Unions.
Plans and specifications are available at the Port of Seattle Procurement website: https://hosting.portseattle.org/sops/#/Solicitations
We are an equal opportunity employer and request sub-bids from all interested firms including disadvantaged, minority, women, and emerging small business enterprises.
We are an AGC member.
Contractor’s License: PACIFPM922J3