West Seattle Corridor Bridge "RE-BID BP#13 Rebar Installation
PROJECT DESCRIPTION: The West Seattle Corridor Bridges Rehabilitation and Strengthening project includes rehabilitation of the West Seattle Bridge and Spokane Street Swing Bridge, and miscellaneous major maintenance work to the elevated structures leading up to the existing bridges. This project will rehabilitate and strengthen both bridges for use by the public.
SOLICITATION AND AWARD SCHEDULE:
Project Advertisement (Request for Proposals): November 17, 2021
Pre-proposal Conference (Virtual): November 30, 2021, at 3:00 PM (PT) and December 1, 2021, at 3:00 PM PT (For a link to attend the virtual meeting please contact Dominic Mascia (206) 620-0630 extension – 405 or email WestSeattleBids@KraemerNA.com)
DBE Requirement: This Prime Contract will have a mandatory DBE goal of 2%, Note: City of Seattle Inclusion Plan requirements are not applicable on FHWA funded projects. See Part 2 of Construction Services Contract for more information. This package has an aspirational DBE goal of 25%
CWA Requirement: This project will have a mandatory Community Workforce Agreement (CWA) requirement. Submitting a proposal, the bidder agrees to participate and meet requirements of the CWA.
Questions Due: December 2, 2021, 5:00 pm (PT) | Answers to questions posted: December 3, 2021 Proposal
FOR MORE INFORMATION CONTACT: Darling Nava, D&I Resource Specialist | 813.947-8586 | darling@zanninc.com
SUBMIT QUESTIONS TO: Dominic Mascia | 206.620.0630 | dmascia@kraemerna.com | WestSeattleBids@KraemerNA.com