You are here

Home » Cle Elum Dam Fish Passage and Juvenile Facility - Intake Structure, Helix and Gate Chamber Project, Cle Elum WA

Cle Elum Dam Fish Passage and Juvenile Facility - Intake Structure, Helix and Gate Chamber Project, Cle Elum WA

Kiewit Infrastructure West Co. requests quotes from Subcontractors, suppliers and service providers, including Small Businesses (SB) defined as SB, SDB, WOSB, HUBZone SB, VOSB & SDVOSB firms in a multitude of Heavy Construction work disciplines in support of our prime contractor proposal to the U.S. Department of the Interior – Bureau of Reclamation. This RFQ is part of the Bureau of Reclamation’s Yakima River Basin Water Enhancement Project and is at the Cle Elum Dam Fish Passage, Juvenile Facility – Solicitation No. 140 R10-18-R-0016

CLE ELUM DAM  -  FISH PASSAGE, JUVENILE FACILITY –         INTAKE STRUCTURE, HELIX, AND GATE CHAMBER  PROJECT

CLE ELUM – KITTITAS COUNTY, WASHINGTON

Prime Contractor:  KIEWIT INFRASTRUCTURE WEST CO.

33455 6TH Avenue South
Federal Way, WA 98003
Tel: (253) 943-4200; Fax: (253) 943-4021

Subcontractor Quotes Due:             June 28, 2018 @ 5:00PM

Sub / Supplier Questions? Contact Dan Jansen (253) 943-4200 Email:  dan.jansen@kiewit.com

Small Business Questions? Contact Dennis Ahl (253) 943-4070 Email:  dennis.ahl@kiewit.com

Bid Date:                                          July 6, 2018 @ 2:00 pm PDT

Project Synopsis / Major Elements: Project includes (6) reinforced concrete intake structures stacked vertically to allow water and fish to be drawn into the juvenile facility over a reservoir water surface fluctuation of 63 feet. Water is controlled at intake structures by an overflow weir crest gate. Water then flows to the juvenile facility through precast concrete conduits, ranging in length from 5 to 500 feet.

The Gate Chamber houses an underground 6-story tall steel structure that supports the guard gate and steel pipe for each of the (6) levels in the existing secant pile shaft. The Helix Chamber houses an underground 48-foot diameter helix structure that dissipates the energy from transporting water and fish from a long vertical distance. The structural support system for the helix is a steel braced frame system that supports a precast concrete flume used to transport water and fish. The Gate and Helix Chambers are fully enclosed by a roof constructed with steel trusses and joists with a reinforced concrete deck

 Subcontractor & Supplier Work Scopes, include:

Concrete - Walls & Slabs; Furnish/pump Concrete;  Precast Concrete Intake Conduits; Fence; Earthworks – Excavation & Backfill; Utilities; Electrical equipment/work;  Elevator (passenger); Environmental protection supplies; Helix Gate Leafs & Handling equipment HVAC system; Intake Bulkhead Gates and Crest Gates; Miscellaneous Metals, Cast Iron & Steel Piping; Landscaping - Topsoil/Seeding;  Quality Assurance & Quality Control; Plumbing, Piping & Mechanical Equipment & Utility work; Furnish/Install Rebar; Roofing Material & hatches; Signage;  Structural Steel - Joist Girders, Steel Doors, Frames and Stairs; Small Tools & Safety Supplies; Sump Pump systems,   Telephone System; Trash Racks; and other work scopes.

The project plans & specifications for Solicitation No. 140 R10-18-R-0016 are on FedBizOpps at the link below:

https://www.fbo.gov/index?s=opportunity&mode=form&id=95c61b4f3f51ff2f9fdfe0105776b44f&tab=core&_cview=1

It is the policy and intent of Kiewit Infrastructure West Co. to provide all qualified/certified small business subcontractors and suppliers with the maximum practicable opportunity to bid upon and participate in the performance of this federal contract should Kiewit become the selected proposer by the government.

In order to assist certified small business subcontractors and suppliers, we will divide scopes of work into economically feasible units, and will assist firms with meeting delivery schedules; providing points of contact regarding bonding, lines of credit, and insurance; and providing small businesses with information to allow them to secure their own equipment in order to maximize Small Business (SB) participation on this project.

 

We are an Equal Opportunity Employer

Closing Date: 
Thursday, June 28, 2018