TO:

UDBE SUBCONTRACTORS

RE:

Washington DOT- F.A. PROJECT NO. NHPP-0054(290)

PROJECT NAME:

STILLAGUAMISH R BR TO HILL DITCH BR PCCP REHAB & PAVING & ADA

COUNTY:

SNOHOMISH AND SKAGIT COUNTIES

BID DATE:

3/28/18 11:00 AM

ENGINEER’S ESTIMATE:

$19,900,000

DBE GOAL:

9%

Services needed: This is a heavy highway project with the typical items of work associated. Myers and Sons Construction is requesting quotes from all qualified subcontractors, trucking firms and suppliers including certified UDBE firms for any part of the following types of work, including but not limited to:

Grading, Drainage, Furnish Ready Mix, Waterproofing, Permeable Ballast, Crushed Surfacing, Seal Sealing Cracks & Joints, HMA, Longitudinal Joint Seal, HMA Sawcut & Seal, Paved Panel Joint Seal, Erosion Control, Planting, Concrete Flatwork, Striping & Marking, Marker, Rumble Strip, Traffic Signal System, Temporary Traffic Control, Concrete Painting, Structure Ex, Surveying, Electrical, Etc. 

Plans & Specifications can be found at:

ftp://ftp.wsdot.wa.gov/contracts/9231-StillaguamishRBrtoHillDitchBrPCCPRehabPavingADA

***All items are open for bid, including items for work normally performed by Myers and Sons Construction. Quotations will be broken down into comparable packages as reasonably necessary. Myers and Sons Construction will work with interested DBE subcontractors to identify opportunities to break down items into economically feasible packages.

ESTIMATOR: Mike Lewis / EMAIL: MLewis@MYERS-SONS.COM / Phone: 916-283-9950

Requirements: 100% performance and payment bonds may be required for the full amount of the subcontract price. Subcontractors must possess a valid contractor's license, DIR registration number, current insurance meeting Myers and Sons Construction's requirements. Subcontractors will be required to sign the standard Myers and Sons Construction Subcontract Agreement. Quotations must be valid for one hundred and twenty (120) days after the specified Contract Award Date by the Owner. Plans and Specifications are available for viewing at our Sacramento office, please contact (916) 283-9950 or mstockton@myers-sons.com.  Please call if you need assistance in obtaining bonding, insurance, equipment, materials and/or supplies or visit our website at www.myers-sons.com for more information. Myers and Sons Construction will work cooperatively with all qualified firms seeking work on this project. Myers and Sons Construction is signatory to the Laborers, Carpenters, Cement Masons and Operating Engineers. Myers and Sons Construction is an equal opportunity employer.

 

 

 

Closing Date: 
Wednesday, March 28, 2018